Paving of Radford Streets

Paving of Radford Streets Begins Fairway Drive

 

Radford, Va- The City of Radford will begin paving streets the week of June 5, 2017.  Crews have already begun prep work for the project and the paving project will begin on Fairway Drive, from Ridgecrest Lane to Buckeye Lane, causing traffic disruptions and detours.  

Paving throughout Radford will take approximately 4-6 weeks and will be done in the following order:

  • Fairway Drive: Ridgecrest Lane to Buckeye Lane
  • Jefferson Street: East Main Street to Tyler Avenue
  • Walker Street: From West Main Street
  • Sixth Street: Walker Street to Harvey Street

Paving Order is subject to change.

If you have any questions regarding the paving project, contact Public Works Superintendent Timmy Lytton at 731-3605.